Three Gorges, NEA, seal deal to form joint venture

Ten months after Nepal Electricity Authority and China Three Gorges International Corporation inked a joint venture agreement, the power authority and CTGIC today signed a deal to form a joint venture company to develop the 750-megawatt West Seti Hydropower Project.Though the NEA board, led by energy secretary, had endorsed the JVA allowing the authority to form a joint venture company to expedite the National Priority Project, CTGIC had taken a longer time to endorse the JVA through its board.
The agreement signed today between NEA Managing Director Kulman Ghising and Yao Feixiong, director of investment department of CTGIC, has paved the way for forming a joint venture company to take forward the project. The joint venture company will develop a business plan to execute the project and the project development agreement will be signed with the Investment Board Nepal.
Maha Prasad Adhikari, CEO of IBN, which looks into implementation of hydropower projects with generation capacity above 500 megawatts, has said that NEA and CTGIC have been told to form the JVC as early as possible since the project initiation date has already passed. As per the memorandum of understanding signed between Investment Board Nepal and the CWE Corp — a subsidiary of CTGIC — in February 2012, construction of the project was supposed to begin in 2014.
The Chinese company has so far carried out the detailed study of the project. The project is likely to be completed in 79 months at a tentative cost of $1.81 billion.
NEA will have 25 per cent equity investment in the JVC, whereas CTGIC will hold three-fourth of the stake in the company. The company has to allocate 10 per cent shares to the public.
Earlier, the Chinese company had put forth a number of conditions to invest in the project, including capitalising the expenses incurred by CTGIC in conducting necessary studies of the project and had sought assurance of market for the electricity generated.
It had also said that since NEA was a joint venture partner in the project, the authority should step in as guarantor to obtain loan (from Exim Bank of China or any other Chinese bank) for investment in the project. The Chinese company has also sought special consideration in share allocation for locals. As per the rules, allotment of 10 per cent shares to locals of the project site area is mandatory for hydel projects. However, CTGIC is unwilling to allot shares to locals. CTGIC had also expressed concerns about tariff policy of NEA.
According to NEA Spokesperson Prabal Adhikari, no deal has been struck on CTGIC concerns. “The joint venture company — West Seti Hydropower Development Company — will deal with the issues once the JVC is formed,” said Adhikari.
The joint venture company will be formed after IBN approves the JVA and the investment proposal of CTGIC. The West Seti Hydropower Development Company will be governed by the board in which CTGIC and NEA will appoint members.
Located in the far western region of Nepal, the 750-MW West Seti will be developed as a reservoir project, with plans to sell the generated electricity in the domestic market. As per the tariff policy of NEA, the project can sell electricity at Rs 12.40 per unit during dry season (from December to May). It has to supply at least 35 per cent of total annual electricity generation during the dry season. Likewise, reservoir projects get Rs 7.10 per unit during wet season (from June to November) for 50 per cent of the total annual electricity generation and the tariff will go down by a similar percentage for the excess energy (above 50 per cent in wet season).
As foreign investment joint venture, the company can sign US dollar-denominated power purchase agreement with NEA for 10 years or until the payback period of foreign loan portion, whichever comes first.

What next?
  • IBN has to endorse JVA and investment proposal of CTGIC
  • JVC will be formed with 75pc stake of CTGIC and 25pc of NEA
  • Board members will be appointed in JVC
  • Business plan or plan of action will be developed
  • Project development agreement will be signed with IBN
  • Environmental Impact Assessment needs to be carried out and approved by the Ministry of Environment
  • Site clearance, land acquisition
  • PPA with NEA will be signed
  • Construction contract will be signed

Comments

Popular posts from this blog

‘Clean India’ mission not ending manual scavenging, activists say

MUMBAI:  A flagship government program to modernise India’s sanitation has failed to tackle the practice of low caste women clearing faeces by hand, and has even exacerbated the problem by building toilets not connected to water supplies, campaigners say. Prime Minister Narendra Modi launched the Swachh Bharat Abhiyan, or Clean India Mission, with much fanfare after he took office in 2014, sweeping a Delhi street with a broom. Since then, thousands of toilets have been built across the country.But Dalit communities, especially women, are still forced to be manual scavengers, a euphemism for clearing faeces from dry toilets and open drains by hand, despite laws to end the practice. The workers have it harder now, activists said. “Swachh Bharat has diverted attention from ending manual scavenging, and makes it seem like the whole country is cleaning. But if that’s the case, then why are people still dying in septic tanks,” said activist Bezwada Wilson. “There is also no dis...

India’s bullet train project re-ignites debate on land for ‘public purpose’

MUMBAI:  Plans for India’s first bullet train, a $17-billion-dollar project, have sparked a debate on the definition of “public purpose” for land acquisitions which have become increasingly contentious. The 500-km- (310-mile-) long high-speed rail link promises to cut travel time between the financial hub of Mumbai and the industrial city of Ahmedabad in Gujarat state by more than half to under three hours. The project, inaugurated earlier this month, will need about 825 hectares (2,000 acres) of land. The government has said it will complete the line by 2022, even as farmers along the proposed route held protests against giving up their land. They may have little say in the matter, as the state has a legal right to take private property for public purposes. But analysts say the definition of what constitutes public purpose needs revisiting, even for infrastructure projects. “When projects – airports, private colleges, bullet trains – benefit only a small percentage of ...

Cahill scores extra-time winner to keep Australia alive

SYDNEY:  Tim Cahill scored twice, including the extra-time winner, as Australia kept their World Cup hopes alive with a 2-1 victory over Syria in the second leg of the Asian playoff on Tuesday. The 3-2 aggregate victory sent the Socceroos into an intercontinental playoff in November against the fourth-placed team in North and Central America and Caribbean (CONCACAF) qualifying with a World Cup spot on the line.Cahill scored Australia’s opener with a trademark header in the 13th minute but it was not until 96 minutes later that he kept his country on course for a fourth successive appearance at the World Cup finals with his 50th international goal. Syria made the perfect start when Omar Al Somah scored in the sixth minute to cancel out Australia’s away-goal advantage from the 1-1 first-leg draw but the war-torn nation’s dreams of securing a maiden World Cup appearance were dashed.