Three Gorges, NEA, seal deal to form joint venture

Ten months after Nepal Electricity Authority and China Three Gorges International Corporation inked a joint venture agreement, the power authority and CTGIC today signed a deal to form a joint venture company to develop the 750-megawatt West Seti Hydropower Project.Though the NEA board, led by energy secretary, had endorsed the JVA allowing the authority to form a joint venture company to expedite the National Priority Project, CTGIC had taken a longer time to endorse the JVA through its board.
The agreement signed today between NEA Managing Director Kulman Ghising and Yao Feixiong, director of investment department of CTGIC, has paved the way for forming a joint venture company to take forward the project. The joint venture company will develop a business plan to execute the project and the project development agreement will be signed with the Investment Board Nepal.
Maha Prasad Adhikari, CEO of IBN, which looks into implementation of hydropower projects with generation capacity above 500 megawatts, has said that NEA and CTGIC have been told to form the JVC as early as possible since the project initiation date has already passed. As per the memorandum of understanding signed between Investment Board Nepal and the CWE Corp — a subsidiary of CTGIC — in February 2012, construction of the project was supposed to begin in 2014.
The Chinese company has so far carried out the detailed study of the project. The project is likely to be completed in 79 months at a tentative cost of $1.81 billion.
NEA will have 25 per cent equity investment in the JVC, whereas CTGIC will hold three-fourth of the stake in the company. The company has to allocate 10 per cent shares to the public.
Earlier, the Chinese company had put forth a number of conditions to invest in the project, including capitalising the expenses incurred by CTGIC in conducting necessary studies of the project and had sought assurance of market for the electricity generated.
It had also said that since NEA was a joint venture partner in the project, the authority should step in as guarantor to obtain loan (from Exim Bank of China or any other Chinese bank) for investment in the project. The Chinese company has also sought special consideration in share allocation for locals. As per the rules, allotment of 10 per cent shares to locals of the project site area is mandatory for hydel projects. However, CTGIC is unwilling to allot shares to locals. CTGIC had also expressed concerns about tariff policy of NEA.
According to NEA Spokesperson Prabal Adhikari, no deal has been struck on CTGIC concerns. “The joint venture company — West Seti Hydropower Development Company — will deal with the issues once the JVC is formed,” said Adhikari.
The joint venture company will be formed after IBN approves the JVA and the investment proposal of CTGIC. The West Seti Hydropower Development Company will be governed by the board in which CTGIC and NEA will appoint members.
Located in the far western region of Nepal, the 750-MW West Seti will be developed as a reservoir project, with plans to sell the generated electricity in the domestic market. As per the tariff policy of NEA, the project can sell electricity at Rs 12.40 per unit during dry season (from December to May). It has to supply at least 35 per cent of total annual electricity generation during the dry season. Likewise, reservoir projects get Rs 7.10 per unit during wet season (from June to November) for 50 per cent of the total annual electricity generation and the tariff will go down by a similar percentage for the excess energy (above 50 per cent in wet season).
As foreign investment joint venture, the company can sign US dollar-denominated power purchase agreement with NEA for 10 years or until the payback period of foreign loan portion, whichever comes first.

What next?
  • IBN has to endorse JVA and investment proposal of CTGIC
  • JVC will be formed with 75pc stake of CTGIC and 25pc of NEA
  • Board members will be appointed in JVC
  • Business plan or plan of action will be developed
  • Project development agreement will be signed with IBN
  • Environmental Impact Assessment needs to be carried out and approved by the Ministry of Environment
  • Site clearance, land acquisition
  • PPA with NEA will be signed
  • Construction contract will be signed

Comments

Popular posts from this blog

India recall pacemen Umesh and Shami for Australia ODIs

MUMBAI:  India have recalled fast bowlers Mohammed Shami and Umesh Yadav for the first three one-day internationals against Australia while they continue to rest their frontline spinners. Yadav and Shami were part of the test squad which blanked Sri Lanka 3-0 but were rested from the subsequent five-match ODI series, which the tourists also swept.Fast bowler Shardul Thakur, who played two matches in the series and took a single wicket, was dropped from the 16-man squad for the series against Australia. The hosts will, however, continue to be without off-spinner Ravichandran Ashwin and left-arm tweaker Ravindra Jadeja for the first three of five matches against Steve Smith’s side. Axar Patel, Kuldeep Yadav and Yuzvendra Chahal will be India’s spinners as the Virat Kohli-led side continues to build toward the 50-over World Cup in 2019 in England and Wales. “The team for the three ODIs against Australia has been selected in line with the rotation policy of the Board and ac...

Naya Shakti flays govt decision to award Budhi Gandaki Project to Chinese company

Baburam Bhattarai-led Naya Shakti Nepal has said that the decision of Pushpa Kamal Dahal-led government to award the contract to construct Budhi Gandaki Hydropower Project to China’s Gezhouba Group Corporation was against the nation’s interest. Issuing a statement on Thursday, the party criticised the government arguing that the decision to hand over the contract to construct 1200 MW project to the Chinese company was condemnable. Bhattarai, who is also a former Prime Minister, said that the government awarded the project to the Chinese company like a blank cheque. The party has also demanded that the government immediately scrap the agreement signed with the Chinese company. The government on June 4 had signed a contract agreement of the project with the Chinese company. Energy Minister Janardan Sharma and a representative from the Chinese company had signed the agreement paper for the construction of 1200MW project. A Cabinet meeting on May 23 had approved the Energy Mi...

कुन प्रदेश को अस्थाई राजधानी कहाँ ? प्रदेश प्रमुख को ?

बुधबार ,३ माघ ( काठमाडौँ ) सरकारले आज सात ओटै प्रदेश को अस्थाई मुकाम र प्रदेश प्रमुख तोकेको छ | बुधबार बसेको मन्त्रि परिसद को बैठक ले सात ओटै प्रदेश को अस्थाई मुकाम र प्रदेश प्रमुख तोकेको हो | जसमा प्रदेश १ को बिराटनगर ,२ को जनकपुर ,३ को हेटौडा र ४ को मुकाम पोखरा तोकेको छ | तेस्तै प्रदेश ५ को रुपन्देही ,६ को सुर्खेत तथा ७ को धनगढी तोकिएको छ |  पदेश प्रमुख मा प्रदेश १ मा डाक्टर गोविन्द सुब्बा ,२ मा रत्नेस्वोरलाल कायस्थ ,३ मा अनुराधा कोइराला, ४ मा बाबुराम कुँवर, ५ मा उमाकान्त झा ,६ मा दुर्गा प्रसाद खनाल र ७ मा मोहनराज मल्ल लाई निउक्त गर्ने सरकारले निर्णय गरेको छ |